CITY GAS DISTRIBUTION (Energy that creates a better path)

Tuesday, March 29, 2022

Flange

A flange is a method of connection pipes, valves, pumps, and other equipment to form a piping system. It is the second and most connection after welding. Flanges provides easy access for cleaning inspection or modification.

Flange Classified :

1- Flange Type 

2- Flange Face 

3- Size 

4- Schedule 

5- Pressure-temperature rating 

6- Material


FLANGE TYPE :

1) Weld neck Flange:

Easy to recognize because of the long-tapered hub. It is the most widely used in process piping. 

  • Used for high pressure and high temperature application 
  • Decrease the high stress concentration at the bottom of the flange. 
  • Used in all pressure class

2) Slip on flange :
The flange slip over the pipe and welded with two filets welds on inside and outside of the flange. It has short service life compared to weld neck flange.

3) Socket weld flange :
This flange is attached to the pipe by a filled weld. The flange has a socket, so the pipe is inserted and fits on the sockets.

  • Can be used in high pressure system.
  • A high skilled welder is required. 
  • There is an expansion gap that is must be 1/16” to prevent residual stress.

4) Threaded Flange :
It has a female thread, so it’s connected to a male thread. Unlike other flanges, threaded flange is connected to the pipe without welding. It is used for low temperature and low-pressure applications.

5) Lap Joint flange :
This flange consists of two parts, which are stub end and the flange. It is used for low pressure applications.

Tuesday, October 19, 2021

Scraping of PE pipe

  1.  During scraping the outer oxidized layer of pipe gets removed and the clean surface is available for Electrofusion jointing. 
  2.  Wipe pipe ends using clean, disposable, lint free material to remove traces of dirt mud, etc. Pipe ends may be washed with clean water if necessary and dried with the lint free material. Ensure pipe end is completely dry before proceeding. 
  3. Mark the area +50 mm beyond the fusion area. 
  4.  For socket fitting measure the depth of penetration of the fitting by placing the socket of the bagged fitting alongside the pipe end and put a witness mark on the pipe at half the fitting length (i.e. Center Mark) to indicate the area to be scraped. Do not remove the fitting from its packaging at this stage. 
  5.  For Saddle fitting mark the area for scraping by putting saddle on pipe without removing the packing. 
  6.  Carefully scrape the whole circumference of the pipe in axial direction over length using a rotary / hand scraper 
  7. When rotary scraper is used, no second scrapping must be performed. 
  8. Wipe the scraped surface with an authorized Isopropanol impregnated pipe wipe or with isopropyl alcohol (IPA) & tissue paper for degreasing the scraped area or soiled fittings. 
  9. Mentholated spirits, acetone, methyl ethyl ketone (MEK) solvents are not recommended for wiping the scraped surface. Ensure the prepared surfaces are completely dry before proceeding.


For Good practices 

a) Always Mark the area to be scraped before scraping. 

b) Use a mirror to inspect while scraping the underneath pipe surface.

c) While scraping remove the entire surface of the pipe over the area indicated, to a depth of approximately 0.3mm. 

d) Pipe must be scraped so that shavings of uniform thickness are formed.

 e) Remember to de-bur the pipe ends after scraping. 

f) Do not touch the prepared pipe surface. 

Procedure For Electrofusion Tapping Tee

  1.  Scrape the necessary pipe surface as per above Mechanical Scraping procedure for saddle type fittings.
  2.  Remove the fitting from its packaging and check the matt of the fitting is clean. Do not touch the fusion zone of the fitting or allow it to be contaminated.
  3.  For fusing tapping tees correctly, sufficient amount of top load should be given properly on fitting. 
  4. Top loading clamp suitable for different diameter range can be used. This clamp can load saddle on to pipe for required load. 
  5. Top loading saddle clamp are light weight for easy transportation on site & are suitable for pipe dia. Up to 500mm. 
  6. Degrease the heating mat with cleaning fluid IPA and white tissue paper. Now fit the tapping tee on pipe with its top attached to the spring of top loading clamp. Tighten the Knob (hand wheel) of clamp until the adjusting spindle (indicator rod) is flush with the top surface

Sunday, May 9, 2021

Commercial NG Burners

 High Pressure Burners (T Type)

Burner Type

Consumption (Kgs/Hr)

T-22

0.9

T-35

1.58

T-50

2.24

T-78

3.56


Avg Load that has to be considered for HP burners is 2 SCMH  


High Pressure Burners (M Type)


Burner Type

Consumption (Kgs/Hr)

M-22

0.9

M-35

1.58

M-50

2.24

M-78

3.56




 V Burner

            

Burner Type

Consumption (Kgs/Hr)

V-300

1.58

V-600

1.58

V-900

1.58

V-1200

1.58




Bunsen Burner (Laboratory Burner)


Consumption - 0.3(Kgs/Hr)

Meters & regulators for I&C Connections & Type of Consumers

Commonly used meters & regulators for I&C Connections 

Tentative
Load SCMH

Meter Size
SCMH

Regulator Size SCMH

Regulator Type

Operating
Pressure mBar

Upto 2.5

3.

3.

Domestic

21

2.5 - 6

6

10

Module / Riser

100

6 - 10

10

10

Module / Riser

100

10 - 25

25

25

Module / Riser

100

25 - 40

40

40

Riser

100

40 — 65

65

65

Riser

100

Above 65

Combination
of above

Combination
of above

Module / Riser

100

Above 65

Customized

Customized

MRS

100 - 500

 









Sunday, April 4, 2021

CRITERIA FOR SELECTION OF METER

  •  Contractual requirement
  •  Rangeability or Turndown ratio
  •  Accuracy required
  •  Pressure requirement
  •  Calibration & maintenance requirement
  •  Size & weight
  •  Installation and maintenance constraints
  •  Operability
  •  Cost
  •  Gas quality
RANGEABILITY

The ratio between Qmin and Qmax, i.e. the minimum and maximum flow rate

respectively for which the meter performs within the maximum permissible errors.

For various type of meters are as follows,

  • Diaphragm meters 1: 150
  • Rotary Positive Displacement meters 1:30 or Better
  • Turbine 1:30 or Better

FILTRATION

Filtration at 50 microns or finer should be fitted to all metering system operating

at pressure above 500 mbar and 27 deg C.

CORRECTORS

Electronic volume correctors will be fitted to all meters operating between flow

range of 800 to 2500 scmd and for flow range above 2500 scmd Electronic flow

meter will be used.

GUIDANCE ON SELECTION

1. Commercial A (Up to 200 scm per day)

a. Normal Commercial :- Small Cafeterias, Restaurants, Caterers, SSI’s etc.

b. Small Commercial :- Office kitchen / Pantries.

c. Concessionary Commercial:- Temples, Charitable trust, Govt. Institution, etc


2. Commercial B (5000 to 25000 SCM per month)

Small scale commercial establishment and industries.


3. Commercial C (above 1000 scm per day)

Big hotels, commercial establishment , hospitals etc.


4. Commercial AC (Only for > 200 TR VAM)

Big hotels, commercial establishment , hospitals etc


5. Industries (Above 1000 SCM per day)

Procedure for Tie in Welding


  • Field welding of pipelines TIE-IN joints shall be done by Shielded Metal Arc Welding (SMAW ) process as per approved WPS.
  • A TIE-IN pit or bell hole of suitable length, depth and width shall be cut to enable to work freely inside the trench.  Proper care shall be taken so as not to allow pit to collapse or pit wall caving in. Necessary supports shall be used wherever required.  An angle of repose of 10º at such area is preferred.
  • In connecting pipes, special items, fittings on joints of differing material thickness as supplied transition piece with 1: 4 taper shall be used  and the welds shall be subjected to Radiographic and Ultrasonic  (wherever applicable) examination.
  • Cut pipe ends shall be examined wherever applicable for laminations by Ultrasonic Testing & Dye Penetrant Testing over distance of 25 mm minimum.
  • Defective pipe length shall be cut back until laminated section is removed and re-beveled for pipe which have been cut, Pipe No., Heat No., Coating yard No., Balance length has to be transferred on to remaining pipe length. The cut piece which is used shall be
  • Designated by XA & the balance pipe length should designate by say pipe B specify XA, XB. Any subsequent cutting of the pipe shall be designated as XBA, XBB.
  • Alignment of the TIE-IN joint shall be done using external hydraulic clamp capable of removing offset and misalignment shall be minimized.
  • Seam orientation of welded pipe shall be selected to ensure that the longitudinal welds shall be staggered in the top 90º of the pipeline or 150 mm. whichever is the less and shall be positioned in the upper half of the pipe, not applicable with HSAW pipes. In case the seams come closer than as defined above, a pup piece of minimum 1.0 m shall be used. For pipes of same wall thickness the offset shall not exceed 3.0 mm.

ALL TIE-IN JOINTS SHALL BE WELDED IN ONE HEAT CYCLE. 

  • TIE-IN shall be done in such a way as to leave minimum stress in the pipe. If any pup end is required for TIE-IN, the minimum length shall not be less than 1.0 meter and two or more such pups shall not be welded together. TIE-IN with two or more pups of length more than 1.0 meter may be used providing a space of entire length of pipe.  In no case more than three welds shall be permitted in a 10 meter length of pipeline. 
  • TIE-IN joint welding including necessary cutting, beveling, grinding and line up etc. shall be carried out as per this procedure and approved WPS.
  • The new field bevels shall be examined visually before offering for ultrasonic (wherever applicable) testing.  All reports of TIE-IN along with NDT reports approval.  Cleaning, Priming, Coating and other activities shall be performed as per approved procedures. 
  • The root gap shall be accurately checked and shall conform to the qualified welding procedure.  All spaces between bars or at least 60% of first pass shall be welded before the clamp is released and pipe remaining adequately supported on each side of the joint.
  • Segments thus welded shall be equally spaced around the circumference of the pipe.  Slag etc. shall be cleaned off and the ends of the pass shall be prepared by grinding, so as to ensure continuity of the weld bead.
  • Qualified welders shall carry out welding.  While welding is in progress, care shall be taken to avoid any kind of movement of the components / pipe, shocks vibration and stresses to prevent occurrence of weld cracks.
  • Electrode starting and finishing points shall be staggered from pass to pass.
  • Arc strikes outside the bevel on the pipe surface shall not be permitted.  Accidental arc strikes shall be repaired as per approved procedure.
  • All finished welds shall be visually inspected for parallel and axial alignment of the work, welds, surface porosity and other surface defects.
  • Parts being welded and the welds shall be protected by windshields made of metallic frame covered by Canvas, whenever necessary, to protect from rain and strong winds.
  • The completed welds shall be covered with asbestos cloth covered by GI sheets, whenever necessary, to protect from bad weather conditions. 
  • For TIE-IN of adjacent sections of pipeline already pressure tested also called golden joints and for final joints, a single length pup or off cuts, which have been hydro statically pre-tested shall be used. 


Wednesday, March 31, 2021

Regulator Sizing Selection

  • Regulators are required to control the downstream pressure in the metering station at one or more points
  • Regulators are sized for maximum anticipated flow requirement with the minimum inlet pressure
  • Although many regulators can operate over a wide flow and pressure ranges, often it is necessary to consider parallel runs to have better control, redundancy and capacity increase
  • Regulators required to operate nearly closed position over long periods of time will tend to have more valve and seat damage, than a unit that is sized to have valve open at least 10%
  • A small regulator can be installed in one line and the larger regulator in the parallel line to handle larger flows up to the required capacity Adequate working space should be available for regulator, plug valves maintenance
  • Regulators with an external control line should have sensing point 5 10 pipe diameters. Control line may be.,1/2 or . depending upon the types of regulator and distance from the pressure sensing point to the regulator
  • Each regulator should have a separate sensing tap and control line.
  • Sensing tap should not be installed on the fittings such as expanders, Tees, Elbows etc.
  • Continuity of operation is the most essential consideration. In case of fail to close regulators, freezing possibilities, it is a good practice to have parallel regulator runs Pilots require clean and dry operating supply, heating taps, small filters can be installed on the pilot lines
  • For safety of regulator operation normally, regulators with relief valve or monitoring regulators are used. For distribution system monitoring operation is preferred whereas relief valve is used for remote locations in general
  • Regulator by-pass and parallel legs are good for performing routine maintenance
  • For fixed factor applications the droop should be in }1% (accuracy). However, for field tapping up to 10% droop is available.

Most control valves are rated with a capacity term called Cv, which is defined as the number of gallons of water per Minute that will flow through the valve with 1 psi pressure drop across the valve.

Cv = Q / (ΔP 62.4/6)

Where Q = quality of water in gpm

ΔP= Pressure drop in psi

Normally Cv or K values of the regulators are given by the manufacturers and formulae for calculating the regulator capacity at critical and non-critical flows are given. The capacity tables can also be used.

If ΔP is less than 8% of (P1) inlet pressure than use formula:

Qh = 76.99×Cv(ΔP(P1)) MSCF/Hr formula - 1

Otherwise use formula

Qh = 54.5 ×Cv (ΔP(P1+P2)/2) formula - 2

Capacity Formula as given by different manufacturers


ROCKWELL 

Q = K (P0(P1-P0)) for P1/P0 < 1.894

Q = K P1/2 for P1/P0 > 1.894

K factor for various orifices

Orifice

 

Single Port

Double Port

1/8”

¼”

3/8”

½”

3/4”

1”

1”

1 ½”

1 ¾”

1/8”

3”

K

33

132

292

520

850

1300

2000

4270

5450

8880

17740

 

 

Example:

P1 = Minimum inlet pressure = 100psia

P0 = outlet pressure = 60 psia

Capacity = 200,000 SCF/Hr

P1/P0 = 100/6- = 1.66 <1.894 use formula 1

200,000 = K (60(100 60))

K = 4081, so from the above table we can select the orifice size of 1 . having K=4270 for monitoring total capacity of both regulators is normally taken as 70% of the capacity of a single regulator. So 2 dia regulator with an orifice size of 1 . will be selected

Find Q for K=4081

Q=4270(60(100-60)) = 209,230 SCF/Hr

If monitoring is required,

calculated K=4081 will become = 5830

Which means now we need an orifice size of 2 1/8 dia. Which is available in 3 dia as RW-441-57S regulator. Its MAOP is 175 psig which can handle inlet pressure of 100 psig

 

FISHER REGULATORS

Capacities can be calculated / regulator selected from the software developed by them

Capacity tables can be consulted

Formulas

(i) Q = P1(abs) (Cg) (1.29) when P0/P1 0.5

(ii) Q = (520/GT) Cg Sin (3417/C1 √Δp/P1) DEG When

P0/P1 >0.5

where

P1 = Inlet Pressure

P0 = Outlet Pressure

C1 = Cg / Cv , Cg = Gas Sizing Co-efficient, See tables from Fisher catalog for 399 regulators

 

Important Considerations

A regulator is usually capable of having more than one orifice size. MAOP of the regulator defines the maximum operating pressure of the regulator body, but pressure rating for different orifices may be less than MAOP. So great care should be taken for the selection of orifice for a particular orifice size, otherwise regulator would not provide tight lock-up.

Search Blog

CITY GAS DISTRIBUTION

Flange

A flange is a method of connection pipes, valves, pumps, and other equipment to form a piping system. It is the second and most connection a...

POSTS